aw11onfire wrote: Dream house :-bd
:ymblushing: :ymblushing: :ymblushing:

Placed deposit and made reservation of the "Dream House" - The Knowsley Plot No.73

\:D/ \:D/ \:D/

From the present construction program and schedule, they will start the work on foundation for Plot No.73 this week with subsequent activities to follow according to the below estimated progress and percentage stage completion:

11 Jan : 05% Progress - Foundation
01 Feb : 15% Progress - Ground Floor
22 Feb : 25% Progress - Block Work to Joists
08 Mar : 35% Progress - Block Work to Eaves
15 Mar : 40% Progress - Roofed Joinery
22 Mar : 45% Progress - Block Work Top Out
29 Mar : 50% Progress - Roof Tiled
05 Apr : 55% Progress - Glazing
19 Apr : 70% Progress - 1st Stage Internal Fixture
03 May : 80% Progress - Plastered
17 May : 90% Progress - 2nd Stage Internal Fixture
07 Jun : 98% Progress - Decorated & Final Fix
14 Jun : 100% Progress - Completion

The house should be ready to be handed over on 15 June 2015

:p :p :p

Re: [House on099] 邊個 AV Room 圖則好 D ?

Posted: Mon Jan 05, 2015 10:52 am
by szekt
Raymond Wan wrote:
aw11onfire wrote: Dream house :-bd
:ymblushing: :ymblushing: :ymblushing:

Placed deposit and made reservation of the "Dream House" - The Knowsley Plot No.73

\:D/ \:D/ \:D/

From the present construction program and schedule, they will start the work on foundation for Plot No.73 this week with subsequent activities to follow according to the below estimated progress and percentage stage completion:

11 Jan : 05% Progress - Foundation
01 Feb : 15% Progress - Ground Floor
22 Feb : 25% Progress - Block Work to Joists
08 Mar : 35% Progress - Block Work to Eaves
15 Mar : 40% Progress - Roofed Joinery
22 Mar : 45% Progress - Block Work Top Out
29 Mar : 50% Progress - Roof Tiled
05 Apr : 55% Progress - Glazing
19 Apr : 70% Progress - 1st Stage Internal Fixture
03 May : 80% Progress - Plastered
17 May : 90% Progress - 2nd Stage Internal Fixture
07 Jun : 98% Progress - Decorated & Final Fix
14 Jun : 100% Progress - Completion

The house should be ready to be handed over on 15 June 2015

:p :p :p
:onion120: :onion120: :onion120:

Re: [House on099] 邊個 AV Room 圖則好 D ?

Posted: Mon Jan 05, 2015 10:55 am
by trytrysin
szekt wrote:
Raymond Wan wrote:
aw11onfire wrote: Dream house :-bd
:ymblushing: :ymblushing: :ymblushing:

Placed deposit and made reservation of the "Dream House" - The Knowsley Plot No.73

\:D/ \:D/ \:D/

From the present construction program and schedule, they will start the work on foundation for Plot No.73 this week with subsequent activities to follow according to the below estimated progress and percentage stage completion:

11 Jan : 05% Progress - Foundation
01 Feb : 15% Progress - Ground Floor
22 Feb : 25% Progress - Block Work to Joists
08 Mar : 35% Progress - Block Work to Eaves
15 Mar : 40% Progress - Roofed Joinery
22 Mar : 45% Progress - Block Work Top Out
29 Mar : 50% Progress - Roof Tiled
05 Apr : 55% Progress - Glazing
19 Apr : 70% Progress - 1st Stage Internal Fixture
03 May : 80% Progress - Plastered
17 May : 90% Progress - 2nd Stage Internal Fixture
07 Jun : 98% Progress - Decorated & Final Fix
14 Jun : 100% Progress - Completion

The house should be ready to be handed over on 15 June 2015

:p :p :p
:onion120: :onion120: :onion120:
Enjoy :-bd :-bd :-bd

Re: [House on099] 邊個 AV Room 圖則好 D ?

Posted: Mon Jan 05, 2015 3:48 pm
by fr888
:-bd :-bd :-bd

Re: [House on099] 邊個 AV Room 圖則好 D ?

Posted: Tue Jan 06, 2015 12:29 am
by aw11onfire
Jealous :fuck:

Re: [House on099] 邊個 AV Room 圖則好 D ?

Posted: Tue Jan 06, 2015 6:27 am
by Raymond Wan
aw11onfire wrote: Jealous :fuck:
:onion116: :onion116: :onion116:

Reserved on 29-12-2014

Paid Reservation Fee on 03-01-2015

:onion200: :onion200: :onion200:

Re: [House on099] 邊個 AV Room 圖則好 D ?

Posted: Tue Jan 06, 2015 6:28 am
by Raymond Wan
:onion14: :onion14: :onion14:

Approx Location of Plot No.73 - The Knowsley

Apposite to the designated green public open space