依據建屋進度,三月中便建至屋頂,要準備及決定另加的室內裝修裝飾
11 Jan : 05% Progress - Foundation
01 Feb : 15% Progress - Ground Floor
22 Feb : 25% Progress - Block Work to Joists
08 Mar : 35% Progress - Block Work to Eaves
15 Mar : 40% Progress - Roofed Joinery
22 Mar : 45% Progress - Block Work Top Out
29 Mar : 50% Progress - Roof Tiled
05 Apr : 55% Progress - Glazing
19 Apr : 70% Progress - 1st Stage Internal Fixture
03 May : 80% Progress - Plastered
17 May : 90% Progress - 2nd Stage Internal Fixture
07 Jun : 98% Progress - Decorated & Final Fix
14 Jun : 100% Progress - Completion



原來屋內間格 - The Knowsley (室內實用面積1,852平方呎)
我會更改屋內間格及房間用途
主要是整合 Living Room 及 Study Room 至稍大的影音房 Audio/Video Room = 25'9" (長) x 12'4" (闊)
以下是發展商建屋已包的室內裝修及設備,但可以從他們提供的"Select"系列中再加錢依個人喜好選擇